projectlist
Deliverables
New Item
|
Filter
Deliverable
Deliverable Description
Estimated Completion Date
Estimated Hours
Actual Hours
Percent Complete
Status
Projected Completion Date
Milestone
1.0 Functional Requirements Document - Preliminary
Preliminary document detailing the functional requirements gathered from the first functional requirements meeting.
1/25/2005
4
Not Started
Functional Requirements Sign-Off
1.1 Functional Requirements Document - Final
Final version of the functional requirements based on the review with the client.
1/27/2005
4
Not Started
Functional Requirements Sign-Off
2.0 Technical Specifications Document - Preliminary
Preliminary Technical Specifications Document based on the Functional Requirements document.
1/28/2005
16
Not Started
Technical Specifications Sign-Off
2.1 Technical Specifications Document - Final
Final vesrion of the Technical Specifications document based on the client review meeting.
2/1/2005
8
Not Started
Technical Specifications Sign-Off
1.2 Test item in the mddle of everything else
New development of some sort of web control
10/31/2006
5
Not Started
Functional Requirements Sign-Off